File #: 1504   
Type: Consent Status: Adopted
File created: 4/10/2020 In control: Public Works Department
On agenda: 4/21/2020 Final action: 4/21/2020
Title: Approval Re: Change Order No. 4B for the Pineda Causeway Grade Separation Overpass - District 4
Attachments: 1. Change Order 4B Contract Approval.pdf, 2. Change Order 4B Contract.pdf
Subject:
Title
Approval Re: Change Order No. 4B for the Pineda Causeway Grade Separation Overpass - District 4
End
Fiscal Impact:
$377,123.58 from the State of Florida Department of Transportation (F.D.O.T.) Joint Participation Agreement grant fund. Any costs not reimbursed by F.D.O.T. for Change Order No. 4B will be reimbursed by the City of Melbourne pursuant to the existing Interlocal Agreement. The County will not incur any costs for Change Order No. 4B.
Dept/Office:
Public Works Department/Finance and Contracts Administration
Requested Action:
Recommendation
It is requested the Board of County Commissioners approve and authorize the Chair to execute Change Order No. 4B in the amount of $377,123.58. It is further requested the Board approve any necessary Budget Change Requests associated with this action.
End
Summary Explanation and Background:
The County and the State of Florida Department of Transportation entered into the Joint Participation Agreement for the Pineda Causeway Grade Separation Overpass project in December 2011. In July 2017, the City of Melbourne and the County entered into an Interlocal Agreement to facilitate the relocation of the City's water main within the project limits.

The County issued the Notice to Proceed to SEMA Construction, Inc. effective July 9, 2018. Following commencement of construction, the contractor encountered unforeseen constructability issues related to existing underground utilities owned by the City of Melbourne. These issues created the need for additional work and significantly impacted the project schedule. On October 22, 2019, the Board approved Change Order 4A which addressed the labor, materials, and equipment costs associated with the additional work due to these unforeseen constructability issues. As indicated on Change Order No. 4A, Change Order No. 4B will address the schedule impacts and contract time extension along with any and all associated costs.

Contract Change Order No. 4B wa...