File #: 2101   
Type: New Business - County Attorney Status: Adopted
File created: 9/8/2020 In control: County Attorney
On agenda: 9/15/2020 Final action: 9/15/2020
Title: Request permission to retain outside counsel for contractor dispute and potential litigation relating to the construction of the Central Disposal Facility (CDF) Slurry Wall Landfill Phase VI Side Slope Closure
Attachments: 1. BCC-36 Legal Services with Outside Counsel.pdf, 2. MLG Fee Agreement_Brevard County_.pdf
Subject:
Title
Request permission to retain outside counsel for contractor dispute and potential litigation relating to the construction of the Central Disposal Facility (CDF) Slurry Wall Landfill Phase VI Side Slope Closure...

End
Fiscal Impact:
Undetermined at this time
Dept/Office:
County Attorney's Office/Solid Waste Department
Requested Action:
Recommendation
Authorize the Solid Waste Department to hire outside counsel to represent the County in resolving construction deficiencies and potential litigation regarding the contract with Thalle Construction Company, Inc. (Thalle) for the construction of the Central Disposal Facility (CDF) Slurry Wall Landfill Phase VI Side Slope Closure project.

End
Summary Explanation and Background:
Construction of the Central Disposal Facility (CDF) Slurry Wall Landfill Phase VI Side Slope Closure project is approaching completion. Solid Waste staff has found latent construction defects with the landfill gas collection system, liner system and stormwater system and notified the contractor. The contractor, Thalle, has hired SCS Engineers to investigate the cause of the defects and Solid Waste staff is monitoring the investigation. The contract price is $11,246,873.60 and there are separate performance and maintenance bonds, each in the amount of the contract value.

Historically, the Board has hired outside counsel to represent the County in construction cases and to assert any breach of contract and liquidated damages claims which may arise. Any breach of contract claim will also involve the surety company which will give rise to the possibility that the County can recover attorney's fees paid, although it is also possible Thalle could recover fees from the county.

It is advisable to involve legal counsel with substantial experience in construction law as this area of practice is a niche specialty that is extremely document and engineering intensive. This office has contacted the Milne Law Group, which is a high...