Title: Adopt Resolution and Release Performance Bond: Armen Groves - District 2 Developer: K. Hovanian at Armen Groves, LLC
Sponsors: Public Works Department
Attachments: 1. ArmenGroves_Resolution_04262025_ADA.pdf, 2. Bond_Contract_ArmenGroves_04262025_ADA.pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Subject:
Title
Adopt Resolution and Release Performance Bond: Armen Groves - District 2
Developer: K. Hovanian at Armen Groves, LLC
End
Fiscal Impact:
None
Dept/Office:
Public Works/Engineering
Requested Action:
Recommendation
In accordance with Section 62-2844(b), it is requested that the Board of County Commissioners adopt the attached Resolution and authorize the Chair to sign the Resolution releasing the Contract and Surety Performance Bond dated December 19, 2023, for Armen Groves.
End
Summary Explanation and Background:
Armen Groves is located east of North Courtenay Parkway and north of Smith Road. The public right-of-way within this plat is Armen Drive. The subdivision contains 36 lots on 27.72 acres.

The Armen Groves subdivision received preliminary plat and final engineering plans on October 28, 2021, and final plat and contract approval on December 19, 2023. The developer posted a Surety Performance Bond for guarantee of the completion of the infrastructure improvements according to the approved plans.

Per Section 62-2809(b)(2), "Construction after final plat recordation: ...the applicant shall provide security required in Section 62-2844 for the performance of such construction..." Section 62-2844(a) states: "An applicant shall be required to secure its performance security of the construction required under this article by a surety bond, letter of credit, savings account, certificate of deposit or execution of a tri-party escrow agreement. Such security shall not be required if a certificate of completion has been issued for all the subdivision improvements prior to final plat recordation." Because the applicant chose to plat the subdivision prior to completion of construction, the applicant entered into a Contract with the Board and posted a Surety Performance Bond to guarantee the completion of the infrastructure improvements according to the approved plans.

As of April 25, 2025, the Armen Groves infrastructure improvements have bee...

Click here for full text