Subject:
Title
Approval Re: Interlocal Agreement with the City of West Melbourne for Sheridan Road Sidewalk Improvements - District 5
End
Fiscal Impact:
The City of West Melbourne will fully fund their portion of the sidewalk improvements, estimated at $366,000. There is no Fiscal Impact to the County.
Dept/Office:
Public Works Department/Finance and Contracts Administration
Requested Action:
Recommendation
It is requested that the Board of County Commissioners:
1) approve and authorize the County Manager to execute the Interlocal Agreement with the City of West Melbourne for the Sheridan Road Sidewalk Improvements;
2) authorize the County Manager to execute any necessary agreement-related documents, such as amendments, contingent upon review and approval by the County Attorney's Office, Risk Management, and Purchasing Services; and
3) authorize the County Manager to approve any Budget Change Requests associated with this action.
End
Summary Explanation and Background:
The County has a capital improvement project to construct sidewalk improvements on Sheridan Road between West Sylvan Drive and Wickham Road. A portion of these improvements lie within the jurisdiction of the City of West Melbourne from the east side of Orange Grove Ave (south side of Sheridan) to just west of Wickham Road.
The County's responsibilities under the proposed ILA include managing the design and construction. Additionally, it also has the authority to enter into appropriate contracts to perform the work associated with the project. The City has agreed that the County will be the lead agency. The City agrees to fully cooperate with and supports the County's work efforts associated with the project and will have the opportunity to review and approve all plans and specifications for the project.
For the construction phase, the City's portion will be a bid option, currently estimated at $366,000. At bid opening, the County will notify the City of the construction cost for the C...