On agenda: 3/17/2026 Final action:
Title: Approval of Task Order No.5 for Jacobs Engineering Group, Inc. for RFQ-7-23-05-South Beaches Wastewater Treatment Plant - 6 MGD Conversion to Advanced Wastewater Treatment.
Attachments: 1. TO 5 SBWWTF 6 MGD AWT Final Design 02202026.pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Subject:
Title
Approval of Task Order No.5 for Jacobs Engineering Group, Inc. for RFQ-7-23-05-South Beaches Wastewater Treatment Plant - 6 MGD Conversion to Advanced Wastewater Treatment.
End
Fiscal Impact:
The cost of completing this Task Order is $2,023,970.
Dept/Office:
Utility Services
Requested Action:
Recommendation
It is requested that the Board approve Task Order No. 5 and further authorize the County Manager to execute future contract task orders and task order amendments.
End
Summary Explanation and Background:
To bring the South Beaches Wastewater Treatment Plant (WWTP) into compliance with Florida Statute 403.086, the existing 6 million gallon per day (MGD) oxidation ditches must be upgraded to meet Advanced Wastewater Treatment (AWT) standards. These improvements are necessary to ensure the facility satisfies current regulatory nutrient removal requirements and continues to protect water quality in the surrounding environment.

The Utility Services Department issued RFQ-7-23-05 for professional engineering services related to the required upgrades and, on January 16, 2024, awarded this contract to Jacobs Engineering Group, Inc. Subsequent task orders have been issued under this RFQ, and the consultant has completed a treatment alternative analysis and preliminary design for the project.

The Department has secured funding from the Florida Department of Environmental Protection (FDEP), including Grant Agreement LPA0421 in the amount of $12M, and an additional $2M from recently awarded, for the design and construction of these improvements. This brings the total non-match FDEP funding to $14M. All task orders issued to date have been funded through these grants.

The Department is now requesting Board approval of Task Order No.5 for Jacobs Engineering Group, Inc., to advance the project from preliminary design to final design. The Department is also requesting authorization for the County Manager to execute future task orders and related amend...