Subject:
Title
Brevard County Federal Shore Protection Project South Reach (D3, D5)
End
Fiscal Impact:
No County funds, to complete approximately $56 million Federally funded beach renourishment project.
Dept/Office:
Natural Resources Management Department
Requested Action:
Recommendation
It is requested that the Board authorize the Chair to execute the following agreement, subject to approval by the County Attorney of final documents substantially in the form of the attached: First Amendment to BOEM Negotiated Agreement No. OCS-A 0554, the Memorandum of Agreement Among the Bureau of Ocean Energy Management (BOEM) and the U.S. Army Corps of Engineers and Brevard County Board of County Commissioners, Regarding the Use of Outer Continental Shelf Sand Resources for Shore Protection and Restoration; and authorize the Chair to sign any future time extensions to this agreement that may be required for project completion, subject to County Attorney approval.
End
Summary Explanation and Background:
On April 20, 2000, Brevard County executed a Project Cooperation Agreement with the U.S. Army Corps of Engineers for initial construction and periodic renourishment of the North and South Reaches of the Brevard County Shore Protection Project over the 50-year life of the Project. On August 31, 2016, Brevard County entered into a Project Partnership Agreement with the Army Corps adding the Mid Reach segment to the Brevard County Shore Protection Project. The Project successfully protected upland property within the project area during Hurricanes Ian and Nicole but suffered significant beach erosion. The County worked with the U.S. Army Corps of Engineers to quantify storm related beach erosion within the area and seek emergency restoration funds. Costs for the work are approximately $18M for the 3.8 mile South Reach and $38M for the 7.8 mile Mid Reach. This project is 100% Federally funded, no County funds are required by the Army Corps to complete this beach construct...
Click here for full text