Brevard County Logo
File #: 5204   
Type: Unfinished Business Status: Adopted
File created: 10/17/2022 In control: Budget
On agenda: 10/25/2022 Final action: 10/25/2022
Title: Allocation of American Rescue Plan Act (ARPA) 2nd Tranche funds to qualified expenditures including Infrastructure, Negative Economic Impacts, Public Health, and Revenue Replacement
Attachments: 1. BOCC Recovery Plan - 7-31-22.pdf
Subject:
Title
Allocation of American Rescue Plan Act (ARPA) 2nd Tranche funds to qualified expenditures including Infrastructure, Negative Economic Impacts, Public Health, and Revenue Replacement
End
Fiscal Impact:
Allocation of up-to $39.6 million of ARPA funding to qualified expenditures
Dept/Office:
Budget Office
Requested Action:
Recommendation
Approval of the recommended allocation of not to exceed $39,597,790 million of ARPA funding for qualified expenditures; Authorize the County Manager to execute all necessary budget change requests for ARPA funded expenditures approved by the Board; Authorize Purchasing Services to issue and award competitive solicitations; Authorize the County Manager to execute all contracts, contract amendments, task orders, work orders and any necessary extensions upon review and approval by the County Attorney's Office, Risk Management and Purchasing Services; Authorize the County Manager to allocate available contingency funds to Board approved ARPA funded expenditures as needed
End
Summary Explanation and Background:
On June 9, 2022, Brevard County received its 2nd Tranche of ARPA funding in the amount of $58,460,088. To date, $18,862,298 has been allocated to the following projects, leaving an available balance of $39,597,790 to be allocated.

Second Tranche Allocation
$ 58,460,088


Board Approved 2nd Tranche Allocations to Date
Amount
Emergency Operations Center
$ 12,200,000
Property Appraiser GIS
$ 1,866,000
COVID Related Medical Claim Reimbursement
$ 3,596,298
Public Safety Radio Upgrade
$ 1,200,000
Total Board Approved Allocations To Date
$ 18,862,298
Remaining 2nd Tranche Available
$ 39,597,790


The U.S. Department of the Treasury's Final Rule incorporated significant changes to include: Improvements to the revenue loss calculation; New eligible water and sewer projects; Expansion of eligible capital expenditure projects; Restoration of Publi...

Click here for full text