Title: Allocation of American Rescue Plan Act (ARPA) 2nd Tranche funds to qualified expenditures including Infrastructure, Negative Economic Impacts, Public Health, and Revenue Replacement
Attachments: 1. BOCC Recovery Plan - 7-31-22.pdf

Subject:

Title

Allocation of American Rescue Plan Act (ARPA) 2nd Tranche funds to qualified expenditures including Infrastructure, Negative Economic Impacts, Public Health, and Revenue Replacement

End

Fiscal Impact:

Allocation of up-to $39.6 million of ARPA funding to qualified expenditures

Dept/Office:

Budget Office

Requested Action:

Recommendation

Approval of the recommended allocation of not to exceed $39,597,790 million of ARPA funding for qualified expenditures;  Authorize the County Manager to execute all necessary budget change requests for ARPA funded expenditures approved by the Board; Authorize Purchasing Services to issue and award competitive solicitations; Authorize the County Manager to execute all contracts, contract amendments, task orders, work orders and any necessary extensions upon review and approval by the County Attorney’s Office, Risk Management and Purchasing Services; Authorize the County Manager to allocate available contingency funds to Board approved ARPA funded expenditures as needed

End

Summary Explanation and Background:

On June 9, 2022, Brevard County received its 2nd Tranche of ARPA funding in the amount of $58,460,088. To date, $18,862,298 has been allocated to the following projects, leaving an available balance of $39,597,790 to be allocated.

 

Second Tranche Allocation

 $      58,460,088

 

 

Board Approved 2nd Tranche Allocations to Date

 Amount

Emergency Operations Center

 $      12,200,000

Property Appraiser GIS

 $         1,866,000

COVID Related Medical Claim Reimbursement

 $         3,596,298

Public Safety Radio Upgrade

 $         1,200,000

Total Board Approved Allocations To Date

 $      18,862,298

Remaining 2nd Tranche Available

 $      39,597,790

 

 

The U.S. Department of the Treasury’s Final Rule incorporated significant changes to include: Improvements to the revenue loss calculation; New eligible water and sewer projects; Expansion of eligible capital expenditure projects; Restoration of Public Sector Capacity; Continuation of Assistance to Impacted Communities. To determine how to most effectively allocate remaining ARPA Funds, County Management coordinated with multiple departments including Utilities Services, Public Works, Natural Resources Management, Housing and Human Services, and Mosquito Control to assess the needs of our community. Priority projects were determined based on shovel readiness and the ability to complete by December 2026, as mandated under ARPA.  

 

Approval is requested to begin the procurement process on the below list of ARPA eligible expenses.  Project estimates were used when developing this list of projects, however, once the procurement process is complete, actual cost of each project may be determined and projects will be updated with the current bid price. These proposed allocations include a contingency in the amount of $5,444,846 (9.31% of the total 2nd tranche), and authorizes the County Manager to shift contingency funds to projects as-needed based on actual bid price.

 

Attached is Brevard County’s 2022 ARPA Recovery Plan Performance Report, which provides additional information on projects being undertaken, including key mandatory performance indicators as required by the U.S. Department of the Treasury.

 

ARPA Category: Infrastructure - Water & Sewer

 

● Clean Water: Stormwater

 

Banana B1124 Elliot Drive Canal Stormwater

 $               79,000

Banana B998 Richland Ave Canal Stormwater

 $               84,000

Huntington Pond Denitrification Retrofit

 $            139,000

Lake Washington Swale - Water Quality Aspect Reduction

 $            200,000

North B116 Lionel Road Modeling & Design of Denitrification Bioreactor

 $            250,000

Banana B1066 Angel Avenue Stormwater

 $            343,000

Street Sweeper-Remove Debris from Roadways

 $            375,000

Dump Trucks, 18 Cubic Yard (2) to Haul Sediment & Aquatic Vegetation

 $            400,000

Basin 958 Pioneer Road Ditch Outfall Stormwater

 $            455,000

Scottsmoor North Stormwater Master Drainage Plan

 $            500,000

Stormwater Performance Retrofits for Existing Ponds

 $            500,000

Equipment for Harvesting Aquatic Weeds

 $            510,000

Hield and Powell Road Stormwater Improvements

 $            575,000

Turpentine Road at Hammock Trail Drainage Culvert Replacement

 $            600,000

West Bay Snug Harbor Sub-Division Stormwater Improvements

 $            600,000

Remote Rain, Wind and Staff Guage Telemetry Stations

 $            750,000

Evans Road at Hibiscus Drainage Improvements

 $            800,000

Track-Hoe W/Long Reach Boom (2) for Wide Canals and Ditch Cleaning

 $            840,000

Oak Park at Suntree Drainage Improvements

 $            950,000

Kaiser Walking Excavators (2) to Maintain Stormwater Systems Ditches & Canals

 $            970,000

Fay Lake Stormwater

 $         1,000,000

Indialantic Stormwater Improvements

 $         1,230,000

Gradall Excavators (3) for Ditch and Vegetated Swale Maintenance

 $         1,560,000

● Clean Water: Centralized Wastewater Collection Conveyance

 

Port St John Inflow & Infiltration Prevention

 $         1,000,000

Sykes Creek Inflow and Infiltration Prevention

 $         1,500,000

Sykes Creek Zone T Septic to Sewer

 $         1,660,944

Viera/I-95 Extend Reuse Transmission

 $         1,800,000

Riverside Drive Force Main & Ground Storage Tank - Phase 2

 $         1,800,000

● Clean Water: Other Sewer Infrastructure

 

Lift Station N-08 Rehabilitation

 $            305,000

Lift Station N-13 Rehabilitation

 $            430,000

Lift Station N-07 Relocation

 $            800,000

● Clean Water: Nonpoint Source

 

North Indian River Dr Road Shoreline Improvement & Drainage Master Plan

 $            750,000

Total Infrastructure - Water & Sewer

 $      23,755,944

 

 

ARPA Category: Negative Economic Impacts - Assistance to Households

● Housing Support: Other Housing Assistance

 

Affordable/Workforce Housing

 $         2,000,000

● Neighborhood Features that Promote Health & Safety

 

Capital Improvements for Parks in the South Area

 $         3,500,000

Total Negative Economic Impacts - Assistance to Households

 $         5,500,000

 

 

ARPA Category: Public Health - Other

 

● Other Public Health Services

 

Mosquito Control Entomology Lab Equipment

 $            300,000

Total Public Health Services

 $            300,000

 

 

ARPA Category: Revenue Replacement

 

● Provision of Government Services

 

Titusville Maintenance Facility Feasibility & Concept Plan

 $            250,000

Cocoa Maintenance Facility Feasibility & Concept Plan

 $            250,000

Merritt Island Maintenance Facility Feasibility & Concept Plan

 $            250,000

Animal Hospital

 $         1,000,000

Wickham Road & Bridge/Fleet Maintenance Facility Modifications

 $         2,847,000

Total Revenue Replacement

 $         4,597,000

 

 

Total Staff Recommendations

 $      34,152,944

Contingency - To be Allocated as Needed (9.31% of Total 2nd Tranche)

 $         5,444,846

Total Allocation

 $      39,597,790

 