Type: Consent Status: Adopted
File created: 5/2/2023 In control: Public Works Department
On agenda: 5/23/2023 Final action: 5/23/2023
Title: Adopt Resolution and Release Performance Bond: Del Webb at Viera, Phase 1 Subdivision - District 4 Developer: The Viera Company
Sponsors: Public Works Department
Attachments: 1. DelWebbPh1_ContractBond_ADA.pdf, 2. DelWebbPh1_Resolution_04292023_ADA.pdf
Subject:
Title
Adopt Resolution and Release Performance Bond: Del Webb at Viera, Phase 1 Subdivision - District 4
Developer: The Viera Company
End
Fiscal Impact:
None
Dept/Office:
Public Works/Engineering
Requested Action:
Recommendation
In accordance with Section 62-2844(b), it is requested that the Board of County Commissioners adopt the attached Resolution and authorize the Chair to sign the Resolution releasing the Contract and Surety Performance Bond dated January 25, 2022 for the above referenced project.
End
Summary Explanation and Background:
The Del Webb at Viera, Phase 1 Subdivision is located within the Viera Development of Regional Impact (DRI), west of Stadium Parkway off of Del Webb Circle and contains a portion of Del Webb Circle along with Coventina Way and a portion of Reef Rock Place. The proposed subdivision contains 45 lots on 35.66 acres.

The Del Webb at Viera, Phase 1 Subdivision received preliminary plat and final engineering plans on October 5, 2021, and final plat and contract approval January 25, 2022. The developer posted a Surety Performance Bond for guarantee of the completion of the infrastructure improvements according to the approved plans.

Per Section 62-2809(b)(2), "Construction after final plat recordation: ...the applicant shall provide security required in Section 62-2844 for the performance of such construction..." Section 62-2844(a) states: "An applicant shall be required to secure its performance security of the construction required under this article by a surety bond, letter of credit, savings account, certificate of deposit or execution of a tri-party escrow agreement. Such security shall not be required if a certificate of completion has been issued for all the subdivision improvements prior to final plat recordation." Because the applicant chose to plat the subdivision prior to completion of construction, the applicant entered into Contract with the Board and posted a Surety Performance Bond to guarantee the...