File #: 4082   
Type: Consent Status: Adopted
File created: 2/28/2022 In control: Parks and Recreation Department
On agenda: 3/8/2022 Final action: 3/8/2022
Title: Allocation, RE: American Rescue Plan Act of 2021 (ARPA) Revenue Replacement Funds to the Florida Coast to Coast Parrish Park Trailhead (District 1)

Subject:

Title

Allocation, RE: American Rescue Plan Act of 2021 (ARPA) Revenue Replacement Funds to the Florida Coast to Coast Parrish Park Trailhead (District 1)

End

Fiscal Impact:

Allocate $737,000 of the $2,000,000 in ARPA revenue replacement funds allocated for Commission District 1 per Board direction on July 20, 2021.

Dept/Office:

Parks and Recreation Department

Requested Action:

Recommendation

It is requested that the Board of County Commissioners acknowledge Commission District 1’s identified use of $737,000 of American Rescue Plan Act of 2021 (ARPA) Revenue Replacement Funds be allocated towards the construction of the Florida Coast to Coast Parrish Park Trailhead in Titusville.

 

End

Summary Explanation and Background:

On July 20, 2021, the Board of County Commissioners approved the allocation of $2 million in American Rescue Plan Act (ARPA) Revenue Replacement funds for general governmental services.  The funds are to be used at the discretion of each Commissioner to address identified needs.  Each Commissioner was asked to bring intended uses back to the Commission and District 1 has identified that $737,000 of ARPA Replacement Revenue funds be obligated to the Florida Coast to Coast Parish Park Trailhead construction project.

 

On March 6, 2018, the Board of County Commissioners authorized the advertisement and award of the RFQ’s/Bids for Design/Engineering Services and award the construction bid for the Florida Coast to Coast Parrish Park Trailhead.  This project is administered by the Florida Department of Transportation (FDOT) through the Local Agency Program (LAP).  Design of the project is complete, and the Notice to Proceed to begin construction is anticipated to be issued in August 2022.  Funding for this project is a partnership between District 1 ARPA Revenue Replacement funds, FDOT, Space Coast Transportation Planning Organization and the Parks and Recreation Department.

Clerk to the Board Instructions: